Quick Answers
When Will the RTS Link Open?

Quick answer
The RTS Link is targeted to start passenger service in February 2027, according to a Malaysia–Singapore joint statement on 2 October 2026. The exact day has not been announced; it depends on independent safety certification and final approvals after testing ends by 31 December 2026.
In this guide
The Johor Bahru–Singapore RTS Link is targeted to open in February 2027. That is the timeline Malaysia’s Ministry of Transport and Singapore’s Land Transport Authority (LTA) gave in a joint release on 2 October 2026, two months later than the earlier end-2026 plan. If you are planning a move, a lease or a purchase around the opening, here is where things stand as of 17 November 2026.
| Step | Timing | Status |
|---|---|---|
| Infrastructure in both countries | – | “Substantially complete” (joint release, 2 Oct 2026) |
| Final system tests and trial runs | By 31 Dec 2026 | In progress |
| Independent safety certification | After testing | Pending |
| Review and acceptance by both governments | After certification | Pending |
| Fare announcement | Expected by end-2026 | Not yet announced |
| Passenger service | Targeted February 2027 | Exact date to be announced jointly |
Why was the opening moved to February 2027?
The operator, RTS Operations (RTSO), needs independent safety certification and final regulatory approvals before carrying passengers. Singapore’s Transport Minister Jeffrey Siow said certification and licensing had been planned for completion before the end of 2026 but were not finished on schedule. No technical fault was given as the reason.
What is still pending?
- Completion of final system tests and trial runs by 31 December 2026.
- Certification by an independent safety assessor.
- Review and acceptance of that certification by both countries.
- A joint announcement of the exact opening date and the fares.
What will the service look like?
Trains are planned to run daily from about 6am to midnight, with a ride of about five minutes between Bukit Chagar and Woodlands North, trains as often as every 3.6 minutes at peak and capacity of about 10,000 passengers per hour in each direction. These are planned figures until the operator publishes its timetable.
For units close to the station, feel free to WhatsApp Darren.
Related guides
- RTS Link progress tracker
- RTS Link JB–Singapore guide
- How much is the RTS Link fare?
- How far is Twin Tower from the RTS station?
Sources
Frequently asked questions
Has the exact RTS Link opening day been announced?
Not as of 17 November 2026. The joint statement of 2 October 2026 gives February 2027 as the target month, and reports say the exact date will be announced jointly by Malaysia and Singapore once safety certification and approvals are complete.
Could the RTS Link be delayed again?
The February 2027 target depends on testing finishing by 31 December 2026, independent safety certification and acceptance by both governments. Infrastructure is described as substantially complete, so the remaining steps are certification and approvals. Check official LTA or Ministry of Transport updates for any change.
Where does the RTS Link run?
It is a roughly 4 km cross-border line between Bukit Chagar station in Johor Bahru and Woodlands North station in Singapore, with no stops in between. The ride is planned to take about five minutes.